Energy projects in the Australian Capital Territory

Updated

The ACT is a small but policy-active market. The Territory generates very little electricity locally and draws the bulk of its supply from the wider NSW grid, but it has used long-term renewable energy contracts to claim 100% renewable electricity for its needs. That makes the ACT an unusual market – more interesting for what it signals about policy ambition and procurement models than for its raw volume of new infrastructure.

Tracked capacity

976 MW total (market scope)

Market snapshot

RenewMap brings together project data, mapping and market context in one place, helping teams track activity across the energy and infrastructure pipeline. Across all projects in the Australian Capital Territory, RenewMap tracks 27 projects with a total capacity of 976 MW.

MW tracked

976

Projects tracked

27

Projects in the pipeline

4

Operating projects

23

Latest project updates

For projects in the Australian Capital Territory there were 0 major updates in the last three months. RenewMap monitors for updates including new projects, development application activity, EPBC updates and status changes. Learn more about updates in RenewMap.

Project development pipeline

RenewMap tracks 4 projects in the Australian Capital Territory across the development, construction, and commissioning phases.

Project name Technology Region Size Status DeveloperDevelopmentApplication
Williamsdale BESSBatteryACT250 MWConstructionEku Energy, EDP RenewablesApproved
CDC Beard BE1Data CentreACT39 MWConstructionApproved
Territory BatteryBatteryACT300 MWDevelopmentNeoenApproved

Largest operating projects

RenewMap tracks 23 operating projects in the Australian Capital Territory, ordered below by capacity.

Project name Technology Region Size Status OwnerDevelopmentApplication
Capital BatteryBatteryACT117 MWOperatingNeoenApproved
CDC Hume Campus TwoData CentreACT51 MWOperatingApproved
CDC Fyshwick Campus OneData CentreACT45 MWOperatingApproved

See the full list of 23 operating projects in the Australian Capital Territory in RenewMap, with related organisations and 100+ more data fields.

Book a demo

Frequently asked questions

How many projects are there in the Australian Capital Territory?
As of May 2026, the Australian Capital Territory has 4 projects in the pipeline and 23 operating.
Who are the top developers in the Australian Capital Territory?
Top developers in the Australian Capital Territory by project count include LGI (3 projects) , Neoen (2 projects) and Elementus Energy (1 project) .
What is the largest operating renewable project in the Australian Capital Territory?
The largest operating renewable project is Royalla Solar Farm at 20 MW.
What project stages are tracked in RenewMap?
RenewMap tracks projects from early development through construction, commissioning and operation. It also tracks projects that have been abandoned, as well as assets that have been decommissioned.

“I’d highly recommend it to anyone in the renewable energy industry looking to grow their business pipeline and stay on top of the key players shaping the sector.”

Andrew Milliss
Sales and Marketing Manager at NEPEAN Power

Get the full picture

RenewMap brings together project data, mapping and market context in one place, helping teams track activity across the energy and infrastructure pipeline.