Inside Victoria’s 65 GW renewable energy pipeline

Victoria has a substantial pipeline of renewable energy projects in development, and in the lead up to the state election this weekend, we’ve been analysing the data to answer a few key questions:
- How much of that capacity has actually progressed through planning?
- Where is approved wind capacity concentrated, and how dependent is it on new transmission infrastructure?
- What is driving the recent increase in approved capacity?
These are important distinctions when trying to understand how much of the development pipeline could realistically progress towards construction.
Last week, The Energy used RenewMap data in its coverage of Victoria’s renewable energy pipeline. It showed that:
- Little of the state’s pipeline has reached construction compared to what is under development
- Batteries are leading new investment decisions, mostly outside of REZs, and no wind has reached FID so far in 2026
- Planning approvals have risen since the Victorian Government’s 2024 planning reforms
The article also looked at which projects rely on planned transmission, including VNI West (the Victoria–NSW Interconnector West) and the Western Renewables Link (WRL).
Digging a little deeper into the underlying data, there are three things that stand out:
- The development pipeline: 42% of Victoria’s pipeline under development is yet to enter planning
- Where the pipeline sits: Most of Victoria’s wind in planning is on the VNI West and WRL corridors
- Approval rate: Annual approval rate is accelerating, boosted by increasing project size
42% of Victoria’s pipeline under development is yet to enter planning
Victoria has 65.1 GW of utility-scale wind, solar and battery projects* in development across 266 projects. That is over five times the 13.2 GW operating, under construction or commissioning today.
42% of the capacity under development has yet to lodge a Development Approval (DA) or Environment Effects Statement (EES). 9% (mostly wind) is waiting on approval of an EES before they can lodge a DA. 13% of capacity is under DA assessment, and 36% holds a DA.
The approved pipeline contains 10.1 GW of wind and solar and 13.3 GW of batteries*.
*Batteries are shown as 4-hour equivalent storage duration.

Most of Victoria’s wind in planning is on the VNI West and WRL corridors
Of the 5.1 GW of approved onshore wind in Victoria, 3.2 GW sits in declared Renewable Energy Zones (REZs) along the transmission corridor for VNI West and/or Western Renewables Link (WRL). 0.9 GW of DA-approved wind sits in REZs west of Melbourne along existing 500 kV lines. Most of the 1 GW of DA-approved wind outside of declared REZs is dispersed across both of these western regions, where the wind resource is strong.
Understanding project development requires looking beyond the individual asset. Where a project sits, what infrastructure it depends on and what else is developing in the same region can all influence its prospects.
The solar pipeline presents a different picture. It is half the size of the wind pipeline and the vast majority of it already holds a DA, but it sits outside of the declared REZs, mostly east of Bendigo or further south-east in Gippsland.

Annual approval rate is accelerating, boosted by increasing project size
The rate at which new capacity is clearing planning approvals in Victoria is accelerating. Victoria was approving less than 2 GW a year in 2022 and 2023. In 2026 YTD, that figure is roughly five-times higher at 9.6 GW. This appears to be largely driven by increased project size given the average approved project size is also five-times higher, from 56 MW in 2022 to 308 MW in 2026.
Batteries have been the largest component most years, growing from 1.0 GW in 2022 to 5.6 GW in 2026. Wind approvals were negligible until 2025, then jumped to 3.7 GW in 2026. A single project, Warracknabeal Energy Park (1,575 MW, approved in October), accounts for a large part of that.
While the number of individual project approvals has not followed a clear upward trend since 2022, more projects have been approved year-on-year since 2024, although solar approvals have fallen significantly.

Looking at capacity alone can give the impression that a much larger number of projects are progressing, when part of the growth is actually being driven by the increasing scale of individual projects, which can be assessed more efficiently than many smaller projects.
Summary
There is clearly a large pipeline of potential renewable energy capacity making its way through the planning process in Victoria. The state has 65.1 GW of utility-scale wind, solar and battery projects under development.
But the data highlights some important considerations when assessing how much of that pipeline can progress in the near term.
- Planning remains a significant hurdle. 42% of development capacity hasn’t yet entered the DA or EES process.
- Each technology has a distinct profile in approvals. Batteries make up most approved capacity and have a deeper pipeline. Significant wind capacity is still being approved at the state level, while much of the solar pipeline has already been approved with a thinner pipeline behind it.
- Transmission is particularly important for wind. Around 3.2 GW of approved wind capacity sits in declared REZs along the VNI West and WRL corridors, making delivery of this infrastructure an important consideration.
- Bigger projects are changing the headline numbers. Approved capacity so far in 2026 is about five times the 2022 level, partly because individual projects are getting bigger.
We will continue to track Victoria’s pipeline daily. RenewMap covers 2,800+ organisations and 35,000+ relationships, connected to more than 4,500 energy and data centre projects across Australia and New Zealand.